Water Utility Upgrades - Phase 1

Oxford, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$40,682
Federal share33%

of $122.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Oxford
Construction start
Jan 22, 2007(actual)
Construction end
Oct 23, 2009(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 24, 2005
  • Construction end7 months lateforecast Mar 31, 2009

Also in Oxford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14513 in the federal list. How to read these figures.