River philip Bridge TCT Connection
Federal contribution
$180,734
Federal share51%
of $352.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Oxford and Area Trail Association
- Construction start
- Apr 13, 2015(actual)
- Construction end
- Dec 23, 2015(actual)
Also in Oxford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50710 in the federal list. How to read these figures.