Replacement of St-Dominique collecting sewer and storm sewer (Laval, Roupe and St-François-Xavier)
Federal contribution
$233,864
Federal share33%
of $701.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2006
2007
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Montebello
- Construction start
- Aug 1, 2006(actual)
- Construction end
- Dec 31, 2006(actual)