Drinking water reservoir, cover plan, unidirectional flushing

Montebello, Quebec

completeDrinking WaterCWWF
Federal contribution
$395,000
Federal share50%

of $790.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Montebello
Construction start
Oct 24, 2017(actual)
Construction end
Oct 15, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2017
  • Construction end5 months earlyforecast Mar 31, 2019

Also in Montebello

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49153 in the federal list. How to read these figures.