Wastewater Treatment Plant Upgrade

Pointe-Verte, New Brunswick

completeWastewaterMRIF
Federal contribution
$33,511
Federal share33%

of $100.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2007
2008
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Pointe-Verte
Construction start
Feb 19, 2007(actual)
Construction end
Mar 18, 2008(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jun 1, 2007
  • Construction end7 months lateforecast Aug 31, 2007