Pointe-Verte - Upgrades to stormwater infrastrucutre and resurfacing of Quay Road
Federal contribution
$543,135
Federal share41%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2022
20232024
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Pointe-Verte
- Construction start
- Sep 25, 2023(actual)
- Construction end
- Nov 1, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 7, 2023
- Construction end4 weeks earlyforecast Nov 30, 2024
Also in Pointe-Verte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63361 in the federal list. How to read these figures.