Maple Avenue Storm Piping and Sidewalk Construction
Charlottetown, Prince Edward Island
Federal contribution
$50,852
Federal share32%
of $159.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Jun 27, 2006(actual)
- Construction end
- Oct 31, 2006(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 1, 2006
- Construction end2 weeks earlyforecast Nov 15, 2006