Cambridge Street / Rilla Road Storm Piping and Sidewalk Construction
Charlottetown, Prince Edward Island
Federal contribution
$116,900
Federal share33%
of $350.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
2007
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Jul 6, 2006(actual)
- Construction end
- Nov 14, 2007(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 1, 2006
- Construction end12 months lateforecast Nov 15, 2006
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14607 in the federal list. How to read these figures.