Back to projects

Trailview Drive Storm Piping

Charlottetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$31,901
Federal share33%

of $95.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Jul 6, 2007(actual)
Construction end
Nov 29, 2007(actual)

Against the original forecast

  • Construction start16 months lateforecast Mar 1, 2006
  • Construction end12 months lateforecast Nov 15, 2006