Upgrade of Elisabeth Street water supply and sewer systems
Federal contribution
$516,693
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2006
2007
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Bedford
- Construction start
- Jun 1, 2007(actual)
- Construction end
- Sep 2, 2007(actual)