Schedule

Announced and approvedSep 11, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Bedford
Construction start
May 25, 2021(actual)
Construction end
Sep 20, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 3, 2021
  • Construction end3 months lateforecast Jun 30, 2024

Also in Bedford