Henri Blanchard Drive Storm Piping
Charlottetown, Prince Edward Island
Federal contribution
$36,887
Federal share18%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
2007
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 14, 2006(actual)
- Construction end
- Mar 1, 2007(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2006
- Construction end3 months lateforecast Nov 15, 2006
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14639 in the federal list. How to read these figures.