Water Distribution Upgrade - Phase III
Federal contribution
$535,277
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2008
200820092010
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Stewiacke
- Construction start
- Jan 28, 2008(actual)
- Construction end
- Sep 22, 2010(actual)
Against the original forecast
- Construction start2.2 years lateforecast Nov 24, 2005
- Construction end6 months lateforecast Mar 31, 2010
Also in Stewiacke