Schedule

Announced and approvedMar 3, 2023
202320242025
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Stewiacke
Construction start
Aug 10, 2023(actual)
Construction end
Feb 10, 2025(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 3, 2023
  • Construction end6 weeks lateforecast Dec 31, 2024