North Town Collector Sewer

Amherst, Nova Scotia

completeWastewaterMRIF
Federal contribution
$467,778
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Amherst
Construction start
Jul 27, 2006(actual)
Construction end
Feb 28, 2009(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 24, 2005
  • Construction end2.2 years lateforecast Dec 15, 2006

Also in Amherst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14675 in the federal list. How to read these figures.