Back to projects

East Victoria Street Rehabilitation

Amherst, Nova Scotia

completeWastewaterCWWF
Federal contribution
$1.1M
$1,100,000
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Amherst
Construction start
Jul 10, 2017(actual)
Construction end
Nov 29, 2017(actual)

Also in Amherst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47249 in the federal list. How to read these figures.