Water Utility Upgrades - Phase 1 and 2
Federal contribution
$171,762
Federal share33%
of $515.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2007
20072008200920102011
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Port Williams
- Construction start
- Jan 22, 2007(actual)
- Construction end
- Jul 6, 2011(actual)
Against the original forecast
- Construction start14 months lateforecast Nov 24, 2005
- Construction end15 months lateforecast Mar 31, 2010
Also in Port Williams
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14699 in the federal list. How to read these figures.