Water Utility Upgrades - Phase 1 and 2

Port Williams, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$171,762
Federal share33%

of $515.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2007
20072008200920102011
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Port Williams
Construction start
Jan 22, 2007(actual)
Construction end
Jul 6, 2011(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 24, 2005
  • Construction end15 months lateforecast Mar 31, 2010