Back to projects

Village of Port Williams - Water & Sewer Main Upgrades

Port Williams, Nova Scotia

completeWastewaterRNIS
Federal contribution
$400,000
Federal share32%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2024
202320242025
Built

Approved 15 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Port Williams
Construction start
Mar 5, 2025(actual)
Construction end
Oct 31, 2025(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 1, 2025

Also in Port Williams

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65499 in the federal list. How to read these figures.