Water Treatment Improvements
Glovertown, Newfoundland and Labrador
Federal contribution
$32,930
Federal share24%
of $137.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2007
20072008
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Glovertown
- Construction start
- Jan 30, 2007(actual)
- Construction end
- Oct 31, 2008(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 1, 2006
- Construction end12 months lateforecast Oct 31, 2007