Station Road Water Storage - Glovertown

Glovertown, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$718,281
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Glovertown
Construction start
Jul 4, 2022(actual)
Construction end
Sep 20, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2022
  • Construction end2 months earlyforecast Nov 28, 2025

Also in Glovertown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53952 in the federal list. How to read these figures.