Station Road Water Storage - Glovertown
Glovertown, Newfoundland and Labrador
Federal contribution
$718,281
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022202320242025
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Glovertown
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Sep 20, 2025(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2022
- Construction end2 months earlyforecast Nov 28, 2025
Also in Glovertown