Back to projects

Road Upgrading and Paving

Glovertown, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$187,530
Federal share33%

of $562.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 14, 2020
2021
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Glovertown
Construction start
Nov 4, 2020(actual)
Construction end
Jun 14, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2020
  • Construction end4 months earlyforecast Sep 30, 2021

Also in Glovertown