Booster Pumping Station
L'Anse au Loup, Newfoundland and Labrador
Federal contribution
$161,488
Federal share33%
of $488.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 25, 2008
20082009
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of L'Anse Au Loup
- Construction start
- Sep 17, 2007(actual)
- Construction end
- Feb 28, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 1, 2007
- Construction end9 months lateforecast Jun 1, 2008