Brook Street Water and Sewer - L'Anse au Loup

L'Anse au Loup, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$345,339
Federal share40%

of $863.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of L’anse au Loup
Construction start
Sep 15, 2020(actual)
Construction end
Sep 3, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 30, 2020
  • Construction end7 months lateforecast Jan 31, 2021

Also in L'Anse au Loup

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54141 in the federal list. How to read these figures.