Increase of water treatment plant production capacity
Federal contribution
$2.4M
$2,408,286
Federal share32%
of $7.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 27, 2008
20092010
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Saint-Anselme
- Construction start
- Jun 2, 2008(actual)
- Construction end
- Oct 31, 2010(actual)
Also in Saint-Anselme
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14801 in the federal list. How to read these figures.