Back to projects

Water System Upgrade

Saint-Anselme, Quebec

completeWastewaterGIS
Federal contribution
$717,344
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022202320242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Anselme
Construction start
Jul 10, 2023(actual)
Construction end
Nov 29, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 19, 2023
  • Construction end5 months lateforecast Jun 30, 2024