Water System Upgrade
Federal contribution
$717,344
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Anselme
- Construction start
- Jul 10, 2023(actual)
- Construction end
- Nov 29, 2024(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 19, 2023
- Construction end5 months lateforecast Jun 30, 2024
Also in Saint-Anselme