Back to projects

New Pumphouse

Hare Bay, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$316,971
Federal share33%

of $956.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2007
20072008
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Hare Bay
Construction start
Jan 30, 2007(actual)
Construction end
Jul 18, 2008(actual)

Against the original forecast

  • Construction start5 months lateforecast Sep 1, 2006
  • Construction end11 months lateforecast Sep 1, 2007

Also in Hare Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14821 in the federal list. How to read these figures.