Back to projects

New Water Intake

Hare Bay, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$50,106
Federal share28%

of $181.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2019
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Hare Bay
Construction start
Apr 19, 2019(actual)
Construction end
Oct 19, 2019(actual)

Against the original forecast

  • Construction start11 months earlyforecast Apr 1, 2020
  • Construction end7 months earlyforecast May 31, 2020

Also in Hare Bay