Sewer System and Water System Enhancements
St. Lawrence, Newfoundland and Labrador
Federal contribution
$205,122
Federal share31%
of $664.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.1 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of St. Lawrence
- Construction start
- Feb 9, 2009(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction start3 months earlyforecast May 1, 2009
- Construction end3.1 years lateforecast Dec 1, 2009
Also in St. Lawrence