Laurentian Avenue Water and Sewer Upgrades
St. Lawrence, Newfoundland and Labrador
Federal contribution
$266,081
Federal share40%
of $665.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
2021
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Lawrence
- Construction start
- Aug 25, 2021(actual)
- Construction end
- Oct 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2021
- Construction end3 months lateforecast Jul 30, 2021
Also in St. Lawrence
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56839 in the federal list. How to read these figures.