Water and Sewer Upgrades
St. Lawrence, Newfoundland and Labrador
Federal contribution
$229,730
Federal share33%
of $689.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of St. Lawrence
- Construction start
- May 9, 2011(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start11 months lateforecast Jun 1, 2010
- Construction end11 months lateforecast Nov 1, 2010
Also in St. Lawrence