Back to projects

Water and Sewer Upgrades

St. Lawrence, Newfoundland and Labrador

completeWastewaterCC Top Up
Federal contribution
$229,730
Federal share33%

of $689.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of St. Lawrence
Construction start
May 9, 2011(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start11 months lateforecast Jun 1, 2010
  • Construction end11 months lateforecast Nov 1, 2010

Also in St. Lawrence

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26721 in the federal list. How to read these figures.