Water Treatment Plant Project - Phase 2

Canso, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$1.0M
$1,005,139
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 8, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Canso
Construction start
Apr 28, 2006(actual)
Construction end
Oct 21, 2009(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 24, 2005
  • Construction end17 months earlyforecast Mar 31, 2011

Also in Canso

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14919 in the federal list. How to read these figures.