Guysborough Wastewater Service Generators
Federal contribution
$140,400
Federal share38%
of $367.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2024
today
20232024202520262027
BuiltForecast
Approved 15 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the district of Guysborough
- Construction start
- Apr 6, 2026(forecast)
- Construction end
- Mar 31, 2027(forecast)