Broadband Infrastructure - Gaspé-Magdalen Islands

Québec, Quebec

completeBroadband And ConnectivityCSIF
Federal contribution
$6.9M
$6,900,000
Federal share50%

of $13.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 3, 2004
20042005
Built

Approved 9 months before the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Dec 1, 2003(actual)
Construction end
Jul 29, 2005(actual)