Water and Sewer Upgrade-Pike’s Lane: Beach Road to Crossroads

Carbonear, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$180,889
Federal share33%

of $542.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20072009201120132015
Built

Approved 8.9 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Carbonear
Construction start
May 8, 2008(actual)
Construction end
Aug 19, 2008(actual)

Against the original forecast

  • Construction start11 months lateforecast Jun 1, 2007
  • Construction end9 months lateforecast Nov 30, 2007

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14953 in the federal list. How to read these figures.