Water Street Water, Sewer and Street Upgrading

Carbonear, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$517,799
Federal share40%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 23, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Apr 17, 2023(actual)
Construction end
Aug 13, 2024(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jun 3, 2023
  • Construction end5 months lateforecast Feb 28, 2024