Valley Road Water, Sewer and Street Upgrading Final Phase
Carbonear, Newfoundland and Labrador
Federal contribution
$426,895
Federal share38%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Carbonear
- Construction start
- Jul 21, 2023(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2023
- Construction end12 months earlyforecast Nov 30, 2024
Also in Carbonear
- Upgrades to Route 70- Interchange at Valley Road and Route 75 - Veterans Memorial Highway$2.2M
- Water System Upgrading$807.0K
- Adelaide Street Water Sewer Storm Street Upgrades Ph2$587.6K
- Water Street Water, Sewer and Street Upgrading$517.8K
- Water Street - Water, Sewer and Street Upgrading Phase 3$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61205 in the federal list. How to read these figures.