Water Storage Tank Upgrade
Woody Point, Newfoundland and Labrador
Federal contribution
$5,937
Federal share6%
of $93.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 25, 2006
20072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Woody Point
- Construction start
- Nov 9, 2006(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2006
- Construction end3.6 years lateforecast Sep 1, 2007
Also in Woody Point