Water Storage Tank Upgrade

Woody Point, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$5,937
Federal share6%

of $93.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 25, 2006
20072008200920102011
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Woody Point
Construction start
Nov 9, 2006(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2006
  • Construction end3.6 years lateforecast Sep 1, 2007

Also in Woody Point

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14973 in the federal list. How to read these figures.