Chlorination Building Upgrade

Woody Point, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$151,334
Federal share50%

of $302.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Woody Point
Construction start
Jun 18, 2018(actual)
Construction end
Jul 23, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2018
  • Construction end4 months lateforecast Mar 31, 2019