Chlorination Building Upgrade
Woody Point, Newfoundland and Labrador
Federal contribution
$151,334
Federal share50%
of $302.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Woody Point
- Construction start
- Jun 18, 2018(actual)
- Construction end
- Jul 23, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2018
- Construction end4 months lateforecast Mar 31, 2019
Also in Woody Point