Upgrades to the Norwood Wastewater Treatment Plant

Norwood, Ontario

completeWastewaterMRIF
Federal contribution
$2.1M
$2,113,333
Federal share33%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
2007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 2, 2007(actual)
Construction end
Jul 29, 2010(actual)

Against the original forecast

  • Construction end16 months lateforecast Mar 31, 2009

Also in Norwood