Upgrades to the Water System and the Installation of Water Meters
Federal contribution
$276,717
Federal share33%
of $830.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Asphodel-Norwood
- Construction start
- Apr 1, 2011(actual)
- Construction end
- Dec 31, 2013(actual)
Against the original forecast
- Construction start4 months lateforecast Nov 30, 2010
Also in Norwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23036 in the federal list. How to read these figures.