Back to projects

Water and Sewer Extension - Terraview Drive

Glovertown, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$67,594
Federal share31%

of $220.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2007
200820092010
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Glovertown
Construction start
Jun 28, 2007(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2007
  • Construction end21 months lateforecast Mar 31, 2008

Also in Glovertown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15386 in the federal list. How to read these figures.