Pembina Bridge

Yellowhead County, Alberta

completeHighways and RoadsMRIF
Federal contribution
$1.6M
$1,620,333
Federal share28%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2007
2007200820092010
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Yellowhead
Construction start
May 27, 2007(actual)
Construction end
Mar 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2007

Also in Yellowhead County