Highway 40 - Passing Lanes
Federal contribution
$3.3M
$3,250,000
Federal share50%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
2011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 1, 2010(actual)
- Construction end
- Nov 15, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2010
- Construction end2 weeks lateforecast Oct 31, 2011
Also in Yellowhead County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39766 in the federal list. How to read these figures.