Alberton Sewer Main Replacement - 2007
Alberton, Prince Edward Island
Federal contribution
$99,410
Federal share33%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.1 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Alberton
- Construction start
- Jun 8, 2008(actual)
- Construction end
- Oct 9, 2009(actual)
Against the original forecast
- Construction start21 months lateforecast Sep 5, 2006
- Construction end2.3 years lateforecast Jun 29, 2007
Also in Alberton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15634 in the federal list. How to read these figures.