Alberton Renewal of Arena

Alberton, Prince Edward Island

completeRecreationCCRIS
Federal contribution
$353,913
Federal share40%

of $884.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
202020212022
Built

Approved 5 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Alberton
Construction start
May 3, 2021(actual)
Construction end
Apr 30, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 15, 2021
  • Construction end5 months lateforecast Nov 30, 2021

Also in Alberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54495 in the federal list. How to read these figures.