Back to projects

Dock River Lift Station Replacement

Alberton, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$110,362
Federal share50%

of $220.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Alberton
Construction start
Nov 15, 2016(actual)
Construction end
Apr 27, 2017(actual)

Also in Alberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47149 in the federal list. How to read these figures.