Sewage Lagoon Expansion - Northern
Federal contribution
$1.1M
$1,089,335
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
200720082009
Built
Approved 9 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Northern Village of LA LOCHE
- Construction start
- Jun 5, 2006(actual)
- Construction end
- Mar 3, 2009(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 3, 2006
- Construction end4 weeks earlyforecast Mar 31, 2009
Also in La Loche
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15636 in the federal list. How to read these figures.