Sewage Pump Station #1, 4 and Poplar Bay Sewer System Upgrades
Federal contribution
$400,000
Federal share50%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201720182019
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Northern Village of La Loche
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Jan 10, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end3 months earlyforecast Mar 31, 2019