Sewage Pump Station #1, 4 and Poplar Bay Sewer System Upgrades

La Loche, Saskatchewan

completeWastewaterCWWF
Federal contribution
$400,000
Federal share50%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
201720182019
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 28, 2017(actual)
Construction end
Jan 10, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2019