Back to projects

Water Supply and Treatment Plant - Northern

Île-à-la-Crosse, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$700,000
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009
Built

Approved 9 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 5, 2006(actual)
Construction end
Jan 20, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 30, 2006
  • Construction end2 months earlyforecast Mar 31, 2009

Also in Île-à-la-Crosse