Back to projects

Sewage Pump Station #1 & 4 Upgrades

Île-à-la-Crosse, Saskatchewan

completeWastewaterCWWF
Federal contribution
$1.6M
$1,650,000
Federal share50%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
201720182019
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 10, 2017(actual)
Construction end
Dec 18, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2019

Also in Île-à-la-Crosse